Achieve planned energy conservation without changing the environment! Here are some examples of how to utilize it.
Here is an introduction to the case studies of implementing ESCO-ONE in hospitals.
In the case of Koga City, Ibaraki Prefecture, it was implemented for 25 air conditioning systems. This resulted in a reduction of 73,561 kWh in annual electricity consumption, a decrease in contracted power (maximum demand) of 49 kW, and an estimated cost reduction of about 1,815,000 yen in electricity charges.
In a hospital in Hachioji City, Tokyo, it was implemented for 34 air conditioning systems, successfully reducing annual electricity consumption by 254,549 kWh, with a decrease in contracted power (maximum demand) of 89 kW, resulting in an estimated cost reduction of about 4,460,000 yen in electricity charges.
[Case Summary]
■ Hospital (Yamanashi Prefecture)
- Implemented for 9 air conditioning systems
- Reduced annual electricity consumption by 24,228 kWh
- Decreased contracted power (maximum demand) by 11 kW
- Estimated cost reduction of about 578,000 yen in electricity charges
*For more details, please refer to the PDF document or feel free to contact us.